Planned diverging trading capacity for Nordic Electricity Exchange Area interconnections during the next 12 months |
||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Areas |
Line | Normal Trading capacity MW |
Updated: 2012-02-22 15:57:36 |
Available Trading capacity MW |
Remarks | |||||||||||||
| From | To | Export | Import |
|
Export | Import | ||||||||||||
| DK2 | DE | Kontek | 600 | 585 | 0 | 0 | 04.06 - 17.06: Yearly maintenance. | |||||||||||
| DK1 | DK2 | Storebælt | 590 | 600 | 0 | 0 | 05.03 - 10.03: Required work in ... | |||||||||||
| DK1 | DK2 | Storebælt | 590 | 600 | 0 | 0 | 28.04 - 02.05: Required maintenance | |||||||||||
| DK1 | DK2 | Storebælt | 590 | 600 | 0 | 0 | 16.06 - 19.06: Work on 400 kV l ... | |||||||||||
| DK1 | DK2 | Storebælt | 590 | 600 | 130 | 130 | 16.07 - 27.07: Work on towers o ... | |||||||||||
| DK1 | DK2 | Storebælt | 590 | 600 | 0 | 0 | 01.08 - 02.08: Work on 400 kV l ... | |||||||||||
| DK1 | DK2 | Storebælt | 590 | 600 | 0 | 0 | 27.08 - 02.09: Yearly maintenance. | |||||||||||
| DK1 | DE | Border between Denmark and Germany | 1500 | 950 | 1500 | 950 | 01.01 - --.--: TenneT TSO GmbH ... | |||||||||||
| DK1 | DE | Border between Denmark and Germany | 1500 | 950 | 1100 | 500 | 13.02 - 02.03: Work on 150 kV line. | |||||||||||
| DK1 | DE | Border between Denmark and Germany | 1500 | 950 | 150 | 150 | 05.03 - 10.03: Required work in ... | |||||||||||
| DK1 | DE | Border between Denmark and Germany | 1500 | 950 | 1100 | 500 | 12.03 - 30.03: Work on 150 kV line. | |||||||||||
| DK1 | DE | Border between Denmark and Germany | 1500 | 950 | 1100 | 500 | 16.04 - 27.04: Work on 150 kV line. | |||||||||||
| DK1 | DE | Border between Denmark and Germany | 1500 | 950 | 200 | 200 | 28.04 - 01.05: Work on 400 kV l ... | |||||||||||
| DK1 | DE | Border between Denmark and Germany | 1500 | 950 | 1100 | 500 | 07.05 - 01.06: Work on 150 kV line. | |||||||||||
| DK1 | DE | Border between Denmark and Germany | 1500 | 950 | 800 | 700 | 22.05 - 23.05: Yearly maintenance. | |||||||||||
| DK1 | DE | Border between Denmark and Germany | 1500 | 950 | 800 | 700 | 24.05 - 25.05: Yearly maintenance. | |||||||||||
| DK1 | DE | Border between Denmark and Germany | 1500 | 950 | 200 | 200 | 16.06 - 19.06: Work on 400 kV l ... | |||||||||||
| DK1 | DE | Border between Denmark and Germany | 1500 | 950 | 200 | 200 | 16.07 - 27.07: Work on towers. ... | |||||||||||
| DK1 | DE | Border between Denmark and Germany | 1500 | 950 | 200 | 200 | 01.08 - 02.08: Work on 400 kV l ... | |||||||||||
| DK1 | NO2 | Skagerrak | 950 | 1000 | 700 | 700 | 05.03 - 10.03: Required work in ... | |||||||||||
| NO2 | DK1 | Skagerrak | 1000 | 1000 | 750 | 750 | 17.04 - 20.04: SK1 will be out ... | |||||||||||
| NO2 | DK1 | Skagerrak | 1000 | 1000 | 750 | 750 | 23.04 - 26.04: SK2 will be out ... | |||||||||||
| DK1 | NO2 | Skagerrak | 950 | 1000 | 700 | 700 | 28.04 - 01.05: Work on 400 kV l ... | |||||||||||
| NO2 | DK1 | Skagerrak | 1000 | 1000 | 750 | 750 | 04.06 - 10.06: SK1 (pol 1) will ... | |||||||||||
| NO2 | DK1 | Skagerrak | 1000 | 1000 | 250 | 250 | 11.06 - 17.06: New estimated st ... | |||||||||||
| DK1 | NO2 | Skagerrak | 950 | 1000 | 700 | 700 | 16.06 - 19.06: Work on 400 kV l ... | |||||||||||
| NO2 | DK1 | Skagerrak | 1000 | 1000 | 750 | 750 | 18.06 - 24.06: New estimated st ... | |||||||||||
| DK1 | NO2 | Skagerrak | 950 | 1000 | 370 | 370 | 16.07 - 27.07: Work on towers o ... | |||||||||||
| DK1 | NO2 | Skagerrak | 950 | 1000 | 500 | 500 | 01.08 - 02.08: Work on 400 kV l ... | |||||||||||
| DK1 | NO2 | Skagerrak | 950 | 1000 | 0 | 0 | 10.09 - 23.09: Yearly maintenance. | |||||||||||
| DK1 | OTH | Cut B (DK1) | 1740 | 1630 | 700 | 700 | 05.03 - 10.03: Required work in ... | |||||||||||
| DK1 | OTH | Cut B (DK1) | 1740 | 1630 | 700 | 700 | 28.04 - 01.05: Work on 400 kV l ... | |||||||||||
| DK1 | OTH | Cut B (DK1) | 1740 | 1630 | 700 | 700 | 16.06 - 19.06: Work on 400 kV l ... | |||||||||||
| DK1 | OTH | Cut B (DK1) | 1740 | 1630 | 370 | 370 | 16.07 - 27.07: Work on 400 kV l ... | |||||||||||
| DK1 | OTH | Cut B (DK1) | 1740 | 1630 | 500 | 500 | 01.08 - 02.08: Work on 400 kV l ... | |||||||||||
| DK1 | SE | Konti-Skan | 740 | 680 | 0 | 0 | 07.05 - 16.05: Yearly maintenance. | |||||||||||
| DK1 | SE3 | Konti-Skan | 740 | 680 | 740 | 100 | 14.05 - 16.05: Yearly maintenan ... | |||||||||||
| DK1 | SE | Konti-Skan | 740 | 680 | 740 | 300 | 30.05 - 01.06: Yearly maintenan ... | |||||||||||
| DK1 | SE | Konti-Skan | 740 | 680 | 370 | 370 | 16.07 - 27.07: Work on towers o ... | |||||||||||
| DK1 | SE | Konti-Skan | 740 | 680 | 500 | 500 | 01.08 - 02.08: Work on 400 kV l ... | |||||||||||
| DK1 | SE | Konti-Skan | 740 | 680 | 740 | 300 | 06.08 - 07.08: Work on 400 kV l ... | |||||||||||
| DK1 | SE3 | Konti-Skan | 740 | 680 | 740 | 450 | 20.08 - 22.08: Single busbar op ... | |||||||||||
| DK1 | SE | Konti-Skan | 740 | 680 | 740 | 300 | 03.09 - 07.09: Original publish ... | |||||||||||
| DK1 | SE | Konti-Skan | 740 | 680 | 740 | 300 | 01.10 - 05.10: Work on 400 kV l ... | |||||||||||
| EST | EST | Peak Load Reserve | 0 | 0 | 0 | 0 | 27.07(2011) - --.--: Information abou ... | |||||||||||
| EST | FI | Estlink | 350 | 350 | 0 | 0 | 13.06 - 14.06: Estlink annual m ... | |||||||||||
| EST | FI | Estlink | 350 | 350 | 0 | 350 | 30.06 - 01.07: Restrictions due ... | |||||||||||
| EST | FI | Estlink | 350 | 350 | 0 | 350 | 04.08 - 05.08: Restrictions due ... | |||||||||||
| EST | FI | Estlink | 350 | 350 | 0 | 350 | 18.08 - 19.08: Restrictions due ... | |||||||||||
| EST | FI | Estlink | 350 | 350 | 0 | 350 | 11.10 - 22.10: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 800 | 750 | 700 | 700 | 13.03 - 19.03: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 800 | 750 | 700 | 700 | 20.03 - 30.03: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 800 | 750 | 550 | 400 | 01.04 - 05.04: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 800 | 750 | 600 | 750 | 21.04 - 01.05: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 750 | 800 | 550 | 350 | 01.06 - 05.06: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 750 | 800 | 700 | 350 | 25.06 - 29.06: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 650 | 700 | 600 | 600 | 02.07 - 09.07: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 650 | 700 | 550 | 400 | 10.07 - 13.07: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 650 | 700 | 600 | 450 | 14.07 - 15.07: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 650 | 700 | 550 | 400 | 16.07 - 17.07: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 650 | 700 | 600 | 600 | 18.07 - 20.07: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 750 | 800 | 650 | 350 | 01.08 - 05.08: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 750 | 800 | 700 | 350 | 06.08 - 24.08: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 800 | 750 | 700 | 700 | 13.09 - 19.09: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 800 | 750 | 700 | 300 | 06.10 - 23.10: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 800 | 750 | 550 | 400 | 24.10 - 06.11: Restrictions due ... | |||||||||||
| EST | LV | Estonia-Latvia | 800 | 750 | 600 | 750 | 07.11 - 11.11: Restrictions due ... | |||||||||||
| EST | RU | Estonia-Russia | 800 | 950 | 750 | 950 | 13.03 - 19.03: Restrictions due ... | |||||||||||
| EST | RU | Estonia-Russia | 800 | 950 | 750 | 950 | 20.03 - 30.03: Restrictions due ... | |||||||||||
| EST | RU | Estonia-Russia | 650 | 950 | 650 | 700 | 21.04 - 01.05: Restrictions due ... | |||||||||||
| EST | RU | Estonia-Russia | 550 | 900 | 550 | 600 | 01.05 - 03.05: Restrictions due ... | |||||||||||
| EST | RU | Estonia-Russia | 550 | 900 | 500 | 450 | 09.05 - 23.05: Restrictions due ... | |||||||||||
| EST | RU | Estonia-Russia | 450 | 700 | 200 | 150 | 13.06 - 24.06: Restrictions due ... | |||||||||||
| EST | RU | Estonia-Russia | 450 | 700 | 400 | 700 | 26.06 - 30.06: Restrictions due ... | |||||||||||
| EST | RU | Estonia-Russia | 550 | 900 | 300 | 250 | 03.09 - 07.09: Restrictions due ... | |||||||||||
| EST | RU | Estonia-Russia | 550 | 900 | 550 | 800 | 13.09 - 19.09: Restrictions due ... | |||||||||||
| EST | RU | Estonia-Russia | 550 | 900 | 500 | 450 | 29.09 - 03.10: Restrictions due ... | |||||||||||
| EST | RU | Estonia-Russia | 800 | 950 | 800 | 850 | 07.11 - 11.11: Restrictions due ... | |||||||||||
| FI | EST | EstLink 2 | 1000 | 1000 | 350 | 350 | 23.12(2010) - 31.01(2014): The main constru ... | |||||||||||
| FI | RU | Finland-Russia | 0 | 1300 | 0 | 400 | 07.07 - 07.08: Vyborg DC-statio ... | |||||||||||
| FI | RU | Finland-Russia | 0 | 1300 | 0 | 1100 | 02.09 - 03.10: Yearly maintenan ... | |||||||||||
| DE | DK1 | Border between TenneT (DE) and Energinet.dk | 950 | 1500 | 150 | 150 | 01.01 - 31.12: ---- New values ... | |||||||||||
| NO3 | NO4 | Central Norway | 200 | 1000 | 200 | 1000 | 28.03(2010) - --.--: Capacity NO4-NO3 ... | |||||||||||
| NO4 | SE1 | T_Trofors-Marka | 700 | 600 | 200 | 400 | 27.03 - 30.03: Condition monitoring | |||||||||||
| NO3 | SE2 | T_Trofors-Marka | 600 | 1000 | 600 | 600 | 27.03 - 30.03: Condition monitoring | |||||||||||
| NO4 | NO3 | T_Trofors-Marka | 1000 | 200 | 400 | 0 | 27.03 - 30.03: Condition monito ... | |||||||||||
| NO4 | SE1 | Rana-Svartisen | 700 | 600 | 600 | 250 | 11.04 - 13.04: Required maintenance | |||||||||||
| NO4 | NO3 | Rana-Svartisen | 1000 | 200 | 600 | 0 | 11.04 - 13.04: Required maintenance | |||||||||||
| NO1 | SE3 | Sylling-Tegneby | 2145 | 2095 | 1650 | 1500 | 23.04 - 27.04: Maintenance | |||||||||||
| NO1 | NO2 | Sylling-Tegneby | 1700 | 2900 | 1300 | 2000 | 23.04 - 27.04: Maintenance | |||||||||||
| NO2 | NO1 | ELSPOT | 2900 | 1700 | 2900 | 1700 | 15.03(2010) - --.--: Capacity NO2-NO1 ... | |||||||||||
| NO1 | NO5 | ELSPOT | 650 | 700 | 650 | 700 | 15.03(2010) - --.--: Capacity NO1-NO5 ... | |||||||||||
| NO2 | NO5 | ELSPOT | 500 | 500 | 500 | 500 | 05.09(2011) - --.--: The capacity NO2 ... | |||||||||||
| NO3 | SE2 | ELSPOT | 600 | 1000 | 600 | 1000 | 01.11(2011) - --.--: New Elspot areas ... | |||||||||||
| NO4 | SE2 | ELSPOT | 250 | 300 | 250 | 300 | 01.11(2011) - --.--: New Elspot areas ... | |||||||||||
| NO4 | SE1 | ELSPOT | 700 | 600 | 700 | 600 | 01.11(2011) - --.--: New Elspot areas ... | |||||||||||
| NO1 | SE3 | NO1-SE | 2145 | 2095 | 0 | 0 | 01.12(2011) - 01.05: During high-load ... | |||||||||||
| NO4 | SE1 | Ofoten-Kobbelv | 700 | 600 | 400 | 200 | 26.03 - 31.03: Required mainten ... | |||||||||||
| NO4 | NO3 | Kobbelv-Ofoten | 1000 | 200 | 750 | 0 | 26.03 - 31.03: Required mainten ... | |||||||||||
| NO4 | SE1 | Salten-Svartisen | 700 | 600 | 500 | 300 | 17.04 - 26.04: Maintenance | |||||||||||
| NO4 | SE2 | Salten-Svartisen | 250 | 300 | 100 | 100 | 17.04 - 26.04: Maintenance | |||||||||||
| NO4 | SE1 | Kobbelv-Ofoten | 700 | 600 | 400 | 200 | 10.09 - 22.09: Maintenance | |||||||||||
| NO3 | SE2 | Nea - Järpstrømmen | 600 | 1000 | 0 | 0 | 05.03 - 09.03: Required maintenance | |||||||||||
| NO3 | SE2 | Nea - Järpstrømmen | 600 | 1000 | 0 | 0 | 12.03 - 16.03: Required maintenance | |||||||||||
| NO3 | SE2 | Nea - Järpstrømmen | 600 | 1000 | 0 | 0 | 19.03 - 23.03: Required maintenance | |||||||||||
| SE3 | SE4 | Busbar Skogssäter | 5300 | 2000 | 4300 | 2000 | 31.03 - 31.03: Single busbar op ... | |||||||||||
| NO1 | SE3 | Busbar Skogssäter | 2145 | 2095 | 1195 | 2095 | 31.03 - 31.03: Single busbar op ... | |||||||||||
| SE3, SE4 | SE3, SE4 | GAS turbines | 0 | 0 | 0 | 0 | 01.01(2011) - --.--: E.ON´s gas turbi ... | |||||||||||
| SE3, SE4 | SE3, SE4 | West Coast corridor | 0 | 0 | 0 | 0 | 01.11(2011) - --.--: Due to high tran ... | |||||||||||
| SE3, SE4 | SE3, SE4 | System protection | 0 | 0 | 0 | 0 | 01.11(2011) - --.--: If low voltages ... | |||||||||||
| SE3, SE4 | SE3, SE4 | Peak Load Reserve | 0 | 0 | 0 | 0 | 16.11(2011) - 15.03: Information abou ... | |||||||||||
| SE1 | FI | SE1-FI | 1500 | 1100 | 1250 | 1100 | 20.02 - 02.03: Start time updat ... | |||||||||||
| SE1 | SE2 | SE1-SE2 | 3300 | 3300 | 3300 | 3300 | 01.11(2011) - --.--: The Net Transfer ... | |||||||||||
| SE1 | SE2 | Svartbyn - Stornorrfors | 3300 | 3300 | 2000 | 3300 | 05.03 - 23.03: Maintenance | |||||||||||
| SE1 | FI | Svartbyn - Stornorrfors | 1500 | 1100 | 600 | 600 | 05.03 - 23.03: Maintenance | |||||||||||
| SE2 | SE3 | Svartbyn - Stornorrfors | 7300 | 7300 | 6800 | 7300 | 05.03 - 23.03: The capacity for ... | |||||||||||
| SE1 | SE2 | SE1-SE2 | 3300 | 3300 | 3200 | 3300 | 26.03 - 04.05: Maintenance on t ... | |||||||||||
| SE2 | SE3 | SE2-SE3 | 7300 | 7300 | 7300 | 7300 | 01.11(2011) - --.--: The Net Transfer ... | |||||||||||
| SE2 | SE3 | SE2-SE3 | 7300 | 7300 | 7200 | 7300 | 03.03 - 03.03: Required maintenance | |||||||||||
| SE2 | SE3 | Midskog-Morgårdshammar | 7300 | 7300 | 6300 | 7300 | 10.03 - 11.03: The capacity for ... | |||||||||||
| SE2 | SE3 | SE2-SE3 | 7300 | 7300 | 7200 | 7300 | 26.03 - 04.05: Maintenance on t ... | |||||||||||
| SE2 | SE3 | Borgvik | 7300 | 7300 | 6000 | 7300 | 09.04 - 13.04: New event stop t ... | |||||||||||
| SE3 | SE4 | SE3-SE4 | 5300 | 2000 | 5300 | 2000 | 01.11(2011) - --.--: The Net Transfer ... | |||||||||||
| SE4 | PL | SwePol Link | 600 | 600 | 0 | 0 | 24.09 - 30.09: Yearly maintenace | |||||||||||